DISCLAIMER: The Graph Chatbot is not programmed to provide explicit or categorical answers to your questions. Rather, it transforms your questions into API requests that are distributed across the various IT services officially administered by EPFL. Its purpose is solely to collect and recommend relevant references to content that you can explore to help you answer your questions.
A rehabilitation scheme at the more than 100 year-old Fully hydro scheme, where the penstock had shown signs of ageing, has involved converting the original single power station into a cascade of three plants, which have been integrated in a municipal water supply system. This paper presents the main stages of the rehabilitation studies, the reasons for the solution adopted, as well as an overview of the construction challenges. The scheme is now nearing completion, with the last small plant scheduled to be commissioned in December.
Touradj Ebrahimi, Yousri Abdeljaoued